One of the most frequent questions we are asked is how soon can we have the extra space?
This is a snap-shot of a recent installation we did for a client in Norwich.
They needed a building fabricated to their requirement which took approximately 21 days and then a further 4 days to install.

End of 1st day, main lifts complete on 50mtr x 20mtr 5.2 side height
2nd day with gable framework and roof covers in place
3rd day with 38mm insulated wall
panels nearing completion
4th day with all roof covers inflated,
and walls and doors in place
If only life were that simple………But actually, that is about the top and bottom of it, apart from the planning and project meetings Jason and Andy attended to bring the whole thing together….
And it’s also interesting that this particular client had the option to take up a unit which was empty and available on the same industrial estate, but chose to use one of our buildings because when they worked out the cost of transport (even locally), staffing and their concerns about the handling of the products, they could see that the option to have one of our buildings installed on their existing site, gave them a much greater degree of control, and at a lower overall cost.
So if you are considering taking space in a third-party warehouse, or are considering taking over a short-term lease on an empty building close by, give us a call to get a quote on having one of our buildings installed at your own premises, because you’ll probably be pleasantly surprised at the cost, and how quickly you could be up and running.
And remember, best of all; you don’t make any minimum commitments to keep our buildings for any period of time either, so if you either lose a contract, or things begin to slow down, you simply give us just seven days notice to off hire it, so you never pay for the space for a day longer than you need it.