Bespoke Temporary Buildings

October 30th, 2009 — 12:23am

I thought you might like to see the result of a contract we recently completed at Linecross Ltd in Rutland…..

Because, due to the rural location of the factory, the local planning department were very conscious
of the need for the buildings to blend in with the green belt environment.

To overcome this, we supplied the buildings with grey roof covers, and olive green walls,
and now; three weeks since arriving on site, Linecross have got an additional 19000 sq ft of secure, covered space…..

Another complication was the limited space within which we could erect the buildings
because the entire floor area where the buildings were installed were used for outside racking…

Our installation team overcame this by building part of the structure, enabling the Linecross staff to
store the goods undercover, and also clear the area for the next phase of the build….

Another important point we had to consider were the new CDM regulations, which are more stringent
now than ever before, especially if a contract takes a certain number of man hours, or indeed, spans over
a specific period of time….

Here’s a couple of pictures, which were taken by our installation team as they left site:

 
 
 
 
This image shows the two buildings, one of 65m x 20m and the other a 30m x 15m; both on 6.2m sideheight.

 
 
 
 
 
 
 
 
 
 
 
 
This is an internal shot of the 65m x 20m building.
 

 
 
 
 
 
 
 
This is a shot from the lane showing the rural location.

Anyway, if you’d like any advice on the points I’ve mentioned, whether it’s available
colours, or indeed, the CDM regs, let me know and I’ll do all I can to help you….

Temporary Buildings

Comment » | CDM Regulations, Company Policies, temporary buildings

How Long Does It Take?

October 20th, 2009 — 7:40pm

One of the most frequent questions we are asked is how soon can we have the extra space?
This is a snap-shot of a recent installation we did for a client in Norwich.
They needed a building fabricated to their requirement which took approximately 21 days and then a further 4 days to install.

They had a flat yard area that was perfect for the installation of a building…
1st morning, 1st lift nearing completion


End of 1st day, main lifts complete on 50mtr x 20mtr 5.2 side height

2nd day with gable framework and roof covers in place

3rd day with 38mm insulated wall
panels nearing completion

4th day with all roof covers inflated,
and walls and doors in place
 

End of day 4, installation complete and ready for handover.

If only life were that simple………But actually, that is about the top and bottom of it, apart from the planning and project meetings Jason and Andy attended to bring the whole thing together….

It took approximately 21 days to fabricate the building, so all in all; it took about one month to provide the additional space the client required.

And it’s also interesting that this particular client had the option to take up a unit which was empty and available on the same industrial estate, but chose to use one of our buildings because when they worked out the cost of transport (even locally), staffing and their concerns about the handling of the products, they could see that the option to have one of our buildings installed on their existing site, gave them a much greater degree of control, and at a lower overall cost.

So if you are considering taking space in a third-party warehouse, or are considering taking over a short-term lease on an empty building close by, give us a call to get a quote on having one of our buildings installed at your own premises, because you’ll probably be pleasantly surprised at the cost, and how quickly you could be up and running.

And remember, best of all; you don’t make any minimum commitments to keep our buildings for any period of time either, so if you either lose a contract, or things begin to slow down, you simply give us just seven days notice to off hire it, so you never pay for the space for a day longer than you need it.

temporary buildings

Comment » | Company Policies, Costs, temporary buildings

Have You Noticed This Happening?

June 4th, 2009 — 1:43pm

At the risk of being deemed a hypocrite
are you, like me seeing a massive increase
in the number of emails coming through right
now?

Emails with ’special offers’ and ‘discount
packages’ from companies, you’d be lucky to
hear from twice a year – normally….

I say ‘normally’, because you’d have had to
have been marooned on an island for the last
12 months not to notice times have changed.

And because of this, there are company owners and
directors all over the country right now; jumping up
and down, throwing mobile phones around the office
and thumping desks screaming

…Sell – sell – sell…..Discount – discount – discount!!

And they’re doing this because they’re in ‘panic mode’.

But here’s what REALLY gets me.

They’re not doing it because they want to help YOU.

They’re doing it because their sales are on the slide…
And they want to help THEMSELVES.

May be you haven’t noticed, or considered this?

But I have, because this is something that’s really close
to my heart.

You see, ever since I started this company, and set
the goal of becoming ‘The Friendliest People In Space’, part
of the thinking was to offer the friendliest terms available.

Terms, which were designed to help YOU, not US ….

And there lies the big difference…Between us, and any
of the companies you get ‘panic’ offers from…

You see, our terms are forever, not just for times of panic.

And I think that’s important for you to know.

Because companies who up until recently would have laughed
you off the phone, had you have asked for a ‘deal’ or
questioned their terms, are now frantically scrambling round
trying to be your best friend.

Pass the sick bucket, can you?

Anyway, as I said at the top, I don’t want you to think
me a hypocrite (because I write to you frequently).

I’m simply writing today to let you know that you
will ALWAYS get the friendliest terms available
with us – whenever you need a temporary building.

You have my personal guarantee on that, you really do.

Thanks for reading this message.

Best

Antony
Temporary Buildings

Comment » | Company Policies, Costs

The Impossible in 21 Days???

November 7th, 2008 — 7:32pm
Frankly, you might think so.
But in 21 days flat The Alternative Parcels Companywent from order to installation of a new 11850 Sq Ft Loading Bay Extension at one of their hubs – and here it is……….
Bay Size Spacings Fabricated To Give Unhindered Access For Vehicles
Could the conventional building approach have done this? Absolutely not.
Would they have been better off hanging around for months and months whilst the ‘civils’ surveying and construction companies all got their act together??
Does it look just as good?
I’ll let you be the judge. In fact, you can come and see some of our buildings whenever you like.
You’ll see that we supplied it without any wall coverings, which changes the calculations for the wind-loading…
So we used oversized chemical fixing anchors for the foot-plates of the building, to compensate for the increased wind up-lift.
Crash barriers were also fitted to the uprights along the one length, to protect the building in the event of collision.
The building is 55mtr x 20mtr, and one interesting feature is, that we fabricated the bays to line up with the doors on their existing building, to give unhindered access for vehicles to reverse up to .
Here’s a picture of it (nearly) finished…..
If you think this kind of arrangement could improve your operation and increase productivity, give us a call.
Let’s talk through what’s possible and see what we can come up with for you.
No obligation – but it could save you a lot of time, worry – and lead to a quick, cost-effective even imaginative solution.
(You’ll find a few examples on http://www.smart-space.co.uk/

Comment » | temporary buildings

Holy Warehouse It’s A Church

November 7th, 2008 — 6:51pm

One of the more unusual inquiries we’ve received recently was from Dean Colum Curry of St. Patrick’s church in Dungannon, Northern Ireland, who called to ask if we could provide a building to be used as a temporary church – of all things, whilst restoration work takes place to the 19th century church…..

And after weeks of consideration and planning, one of our crews has completed the building, which is now being used for services throughout the week…..

The job was made all the more difficult because the car-park where we installed the building has a 2.5m drop over the length of the building, so a steel frame floor was provided to level the surface, and the results are impressive to say the least……..

“Church interior with seating for 700″

The church has purchased a brand new 35mtr x 15mtr insulated building and ordered double glazed windows along one side, which overlook the convent, and provide natural daylight too.

“Raised floor with emergency escape door”

Another clever use of space is the area underneath the raised end of the building, which is to be used for church council meetings, and is accessed through the dooras shown at the bottom of the picture above….

The building has created quite a stir locally and the Northern Ireland press have been involved too, because it’s believed this is the first time atemporary ‘warehouse’ building has been used for this purpose….

So if there’s ever a time when you, or an organisation you know of, needs additional space – for any purpose – let us know and it just may be possible to create the setting you’ve got in mind…….
At a fraction of the cost of building……

Almost anything is possible with a bit of vision, and a lot of planning (which we’ll take care of)

Comment » | Costs, temporary buildings

Uses for Temporary Buildings

October 2nd, 2006 — 3:25pm


Whilst it may sound like a cliché, Smart-space temporary buildings can be used for almost any application. Initially, they were simply used as a storage warehouse – for seasonal peaks to keep valuable goods under cover, secure and dry.

Requests came in for temporary buildings for a variety of uses – loading bays for goods inwards checking – again, valuable stock is protected. Temporary buildings have been used at a sewage treatment plant for producing ‘cakes’, (just in case you’re wondering – this structure was subsequently scrapped), and by a forensic investigation team analysing building remains for evidence collection.

Smart-space temporary buildings lend themselves superbly for use as car showrooms, particularly when fitted with large windows.

Other applications have been for dining rooms and restaurants; sometimes during a refurbishment, others that have stayed as a permanent site.
Schools and colleges use the temporary buildings for examination halls – they are not just warehouses for storage of goods but can also create an ambient working environment complete with heating, air-conditioning and insulation.

Comment » | temporary buildings

Blot on the Landscape?

October 2nd, 2006 — 2:44pm

Do temporary buildings stick out like a ‘sore thumb’ or do they blend into their surroundings – a factory yard, car showroom or airport arrivals lounge?

When looking for extra space, the last thing a client wants to feel is that they have degraded the company image in any way. One of the great advantages of a Smart-space temporary building is their flexibility – be it size, colour or access.

Whilst basically developed from the same structure, Smart-space temporary buildings can be tailored to the user’s needs – a car showroom with large windows, a goods inwards bay with electric roller shutter access, or an International arrivals lounge at an airport.

Temporary buildings can be manufactured to order in corporate livery if need be. Walls can be enhanced with signage and the materials used means that they can be cleaned easily.

With Smart-space temporary buildings, there is no need to tolerate Heath Robinson structures like this one, cobbled together.

(this building is MOST DEFINATELY NOT one of ours!)

Installing a temporary building is an ideal way to overcome short term space problems without losing production time or damaging goods. They can be used to enhance your image whilst waiting to move premises or trialling new procedures.

Comment » | Company Policies, temporary buildings

It’s not a flapping tent is it?

October 2nd, 2006 — 2:39pm

In the early days of our temporary buildings industry, this was a common question from sceptical warehouse managers.

Of course, the industry HAD grown from the events industry – framed structures were indeed used as were marquees, but our new generation of Smart-space temporary buildings are far removed from those early days.

The Smart-space temporary buildings now used are built to German Industrial Norms DIN 4112, using a steel framework with a range of roof and wall options. They are windproof and watertight, meeting stringent requirements for wind and snow load, with a capability of withstanding even the most severe weather conditions. Even so, our trained erectors install them in a fraction of the time it takes to install steel framed buildings.

See a typical specification here…

These temporary buildings bolt onto your existing ground service – concrete, tarmac or hardcore – they all work well, so there is minimal preparation required by the client. This of course also saves upheaval and time – these buildings can be erected and ready to use within 72 hours (depending upon their size of course).

Whilst we refer to these structures as temporary buildings – they can be used indefinately; the temporary aspect really only refers to ease that they can be installed and removed.

Comment » | temporary buildings

Back to top