Tag: bespoke


Bespoke Temporary Buildings

October 30th, 2009 — 12:23am

I thought you might like to see the result of a contract we recently completed at Linecross Ltd in Rutland…..

Because, due to the rural location of the factory, the local planning department were very conscious
of the need for the buildings to blend in with the green belt environment.

To overcome this, we supplied the buildings with grey roof covers, and olive green walls,
and now; three weeks since arriving on site, Linecross have got an additional 19000 sq ft of secure, covered space…..

Another complication was the limited space within which we could erect the buildings
because the entire floor area where the buildings were installed were used for outside racking…

Our installation team overcame this by building part of the structure, enabling the Linecross staff to
store the goods undercover, and also clear the area for the next phase of the build….

Another important point we had to consider were the new CDM regulations, which are more stringent
now than ever before, especially if a contract takes a certain number of man hours, or indeed, spans over
a specific period of time….

Here’s a couple of pictures, which were taken by our installation team as they left site:

 
 
 
 
This image shows the two buildings, one of 65m x 20m and the other a 30m x 15m; both on 6.2m sideheight.

 
 
 
 
 
 
 
 
 
 
 
 
This is an internal shot of the 65m x 20m building.
 

 
 
 
 
 
 
 
This is a shot from the lane showing the rural location.

Anyway, if you’d like any advice on the points I’ve mentioned, whether it’s available
colours, or indeed, the CDM regs, let me know and I’ll do all I can to help you….

Temporary Buildings

Comment » | CDM Regulations, Company Policies, temporary buildings

How Long Does It Take?

October 20th, 2009 — 7:40pm

One of the most frequent questions we are asked is how soon can we have the extra space?
This is a snap-shot of a recent installation we did for a client in Norwich.
They needed a building fabricated to their requirement which took approximately 21 days and then a further 4 days to install.

They had a flat yard area that was perfect for the installation of a building…
1st morning, 1st lift nearing completion


End of 1st day, main lifts complete on 50mtr x 20mtr 5.2 side height

2nd day with gable framework and roof covers in place

3rd day with 38mm insulated wall
panels nearing completion

4th day with all roof covers inflated,
and walls and doors in place
 

End of day 4, installation complete and ready for handover.

If only life were that simple………But actually, that is about the top and bottom of it, apart from the planning and project meetings Jason and Andy attended to bring the whole thing together….

It took approximately 21 days to fabricate the building, so all in all; it took about one month to provide the additional space the client required.

And it’s also interesting that this particular client had the option to take up a unit which was empty and available on the same industrial estate, but chose to use one of our buildings because when they worked out the cost of transport (even locally), staffing and their concerns about the handling of the products, they could see that the option to have one of our buildings installed on their existing site, gave them a much greater degree of control, and at a lower overall cost.

So if you are considering taking space in a third-party warehouse, or are considering taking over a short-term lease on an empty building close by, give us a call to get a quote on having one of our buildings installed at your own premises, because you’ll probably be pleasantly surprised at the cost, and how quickly you could be up and running.

And remember, best of all; you don’t make any minimum commitments to keep our buildings for any period of time either, so if you either lose a contract, or things begin to slow down, you simply give us just seven days notice to off hire it, so you never pay for the space for a day longer than you need it.

temporary buildings

Comment » | Company Policies, Costs, temporary buildings

The Impossible in 21 Days???

November 7th, 2008 — 7:32pm
Frankly, you might think so.
But in 21 days flat The Alternative Parcels Companywent from order to installation of a new 11850 Sq Ft Loading Bay Extension at one of their hubs – and here it is……….
Bay Size Spacings Fabricated To Give Unhindered Access For Vehicles
Could the conventional building approach have done this? Absolutely not.
Would they have been better off hanging around for months and months whilst the ‘civils’ surveying and construction companies all got their act together??
Does it look just as good?
I’ll let you be the judge. In fact, you can come and see some of our buildings whenever you like.
You’ll see that we supplied it without any wall coverings, which changes the calculations for the wind-loading…
So we used oversized chemical fixing anchors for the foot-plates of the building, to compensate for the increased wind up-lift.
Crash barriers were also fitted to the uprights along the one length, to protect the building in the event of collision.
The building is 55mtr x 20mtr, and one interesting feature is, that we fabricated the bays to line up with the doors on their existing building, to give unhindered access for vehicles to reverse up to .
Here’s a picture of it (nearly) finished…..
If you think this kind of arrangement could improve your operation and increase productivity, give us a call.
Let’s talk through what’s possible and see what we can come up with for you.
No obligation – but it could save you a lot of time, worry – and lead to a quick, cost-effective even imaginative solution.
(You’ll find a few examples on http://www.smart-space.co.uk/

Comment » | temporary buildings

Holy Warehouse It’s A Church

November 7th, 2008 — 6:51pm

One of the more unusual inquiries we’ve received recently was from Dean Colum Curry of St. Patrick’s church in Dungannon, Northern Ireland, who called to ask if we could provide a building to be used as a temporary church – of all things, whilst restoration work takes place to the 19th century church…..

And after weeks of consideration and planning, one of our crews has completed the building, which is now being used for services throughout the week…..

The job was made all the more difficult because the car-park where we installed the building has a 2.5m drop over the length of the building, so a steel frame floor was provided to level the surface, and the results are impressive to say the least……..

“Church interior with seating for 700″

The church has purchased a brand new 35mtr x 15mtr insulated building and ordered double glazed windows along one side, which overlook the convent, and provide natural daylight too.

“Raised floor with emergency escape door”

Another clever use of space is the area underneath the raised end of the building, which is to be used for church council meetings, and is accessed through the dooras shown at the bottom of the picture above….

The building has created quite a stir locally and the Northern Ireland press have been involved too, because it’s believed this is the first time atemporary ‘warehouse’ building has been used for this purpose….

So if there’s ever a time when you, or an organisation you know of, needs additional space – for any purpose – let us know and it just may be possible to create the setting you’ve got in mind…….
At a fraction of the cost of building……

Almost anything is possible with a bit of vision, and a lot of planning (which we’ll take care of)

Comment » | Costs, temporary buildings

Back to top